Storefront Location Request for Proposal

Lawrence Public Library would like to announce a request for proposals (RFP) to renovate the new storefront location at 3514 Clinton Parkway.

LAWRENCE, Kan. — Lawrence Public Library would like to announce a request for proposals (RFP) to renovate the new storefront location at 3514 Clinton Parkway. The full details of the RFP can be found below.

A printer-friendly version of the RFP is also available for download.

Lawrence Public Library Storefront Location Request for Proposal

November 17, 2026

Interested parties can contact Brad Allen, City Librarian, for our recommended proposal format.

Contact: Brad Allen, City Librarian

Email: [email protected]

Phone: 785-843-3833 x102

Overview

The Lawrence Public Library has signed a lease for commercial property in the Parkway Shopping Center at 3514 Clinton Parkway with the intent of creating a new space to provide services and programs for their patrons who identified the want and need for a location in southwest Lawrence.

RFP Intent

The purpose of this RFP is to identify a General Contractor to collaborate with LPL in renovating the current space to allow the library to build out their “proof of concept” incubator space that will integrate flexible areas to provide services for material circulation, children and teen programs, meetings rooms, and a “third space” community living room. The current space will require little change in layout with the general direction of achieving a “white box” commercial space. 

Project Scope

The Contractor will be responsible for all labor, materials, management, and insurance coverage to renovate the current space to meet the following criteria:

  • Necessary documents for the construction permit for the tenant improvements.
  • Remove existing cabinetry in areas 1, 2, 3, 4, 5 & 8.
  • Demo the glass block wall on the north side of area 2 and repair drywall soffit above wall where block was removed.
  • Demo center partition wall in area 8.
  • Remove shelving, brackets, and supports in area 4.
  • Remove all signage in area 1.
  • Relocate door in area 5 from west to east wall (entering from area 4); frame and drywall opening where the door was removed.
  • Build wall in area 6 to create a new meeting room; integrate a 3’ door with glass lite and a 36” glass side light.
  • Frame partition with two 3’x’7’ doors with glass lite to enclose area 8.
  • Provide new casework in area 3, including new sink and faucet.
  • Patch and prep ALL walls throughout the space for new paint finish.
  • Install carpet tile over existing LVT, including surface prep in area 1.
  • Install carpet tile, including surface level and prep in areas 2, 5, 6 & 7
  • Remove existing VCT and replace with new VCT in area 3
  • Remove existing and install new vinyl cover base throughout
  • Modify and patch existing ceiling grid and tile as necessary to provide consistent lay-in ceiling throughout the space.
  • Patch and repair floor throughout the space in preparation for new flooring materials.
  • Remove plumbing fixtures and cap piping in areas 4, 5, 6 & 8.
  • HVAC, modify / relocate and ductwork, supply and return in area 6 & 7.
  • Modify Fire sprinkler throughout as necessary from integrated changes.
  • In area 1, replace cover plates on operable electrical floor outlets and remove and terminate any non-operable locations.
  • Disconnect and remove devices and terminate wiring in areas 5 & 8 (in casework that was removed).
  • Remove floor boxes and terminate wiring in area 7.
  • Remove track lighting and modify ceiling in area 7.
  • There will be additional electrical as the LPL Technology Team develops their program for the facility, which will be integrated with the selected contractor once the tech plan is in place.

Milestones

I. Request for Proposal Invitations

The LPL Board of Trustees meets on November 16 and will discuss authorizing the library to move forward with the RFP. Upon their approval, the library anticipates having the RFP invitations out by November 17.

II. Site Visit Walk-Through

Once the RFP is released, we will plan a walk-through of the space on November 20 at 10:00 am.

III. Proposals Due

Construction service proposals will be due to the LPL on December 8 at 2:00 pm.

IV. Project Schedule

The tentative project timeline is:

  • Proposal Review and approval by December 15. 
  • Contractor to submit permit documents for LPL review by December 29.
  • Contractor to submit permit documents to the City by January 5, 2027.
  • Contractor starts work pending city permit review by January 18.
  • Contractor to be substantially complete with tenant improvements by March 15.

Floor plan for the library's storefront location.

Color-coded labels of library spaces overlay the floor plan for the library's storefront location.